Time Cost Analysis

Estimates cost in time for software development using either Function Points, Basic COCOMO, or Intermediate COCOMO.

CLI

Description

The cli version is built in C++. To view the documentation for it click here

How to Use

  • To run the program just open up a command line and run make all
  • Then run tca.exe
  • Note that you will need to have make and gcc installed. If you're on Windows, I recommend using MinGW.

Web

Description

The web version is built in JavaScript and is much easier to use since it has a GUI.

How to Use

To use the web version, you can simply click here and start using it immediately inside of your browser.

Function Points

Algorithm

N = number of that type of component

C = component complexity value

I = influence value

Unadjusted Function Points (UFP) = (N0 x C0) + (N1 x C1) + (N2 x C2)...

Degree of Influence (DI) = I0 + I1 + I2 + ... + I14

Technical Complexity Factor (TCF) = 0.65 + (0.01 x DI)

Adjusted Function Points (FP)= UFP x TCF

Component Complexities

Component Simple Average Complex
Input item 3 4 6
Output item 4 5 7
Inquiry 3 4 6
Master file 7 10 15
Interface 5 7 10

Technical Factors

These are used for degrees of influence and range from values 0 for no influence to 5 for strong influence

  1. Data communication
  2. Distributed data processing
  3. Performance criteria
  4. Heavily utilized hardware
  5. High transaction rates
  6. Online data entry
  7. End-user efficiency
  8. Online updating
  9. Complex computations
  10. Reusability
  11. Ease of installation
  12. Ease of operation
  13. Portability
  14. Maintainability

COCOMO

Basic COCOMO

Algorithm

KDSI = estimated lines of code in thousands

A and B are constants given by project size.

Person-Months = A x KDSI B

Project Complexity Constants

Type Size A B
Organic Small 2.4 1.05
Semi-detached Medium 3.0 1.12
Embedded Complex 3.6 1.20

Intermediate COCOMO

Algorithm

KDSI = estimated lines of code in thousands

A and B are constants given by project size.

Person-Months (basic) = A x KDSI B

C = cost driver complexity score

Cost Driver Total = C0 * C1 * C2 * ... * C14

Person-Months (intermediate) = Person-Months (basic) x Cost Driver Total

Project Complexity Constants

Type Size A B
Organic Small 3.2 1.05
Semi-detached Medium 3.0 1.12
Embedded Complex 2.8 1.20

Cost Drivers

Cost Driver Very Low Low Nominal High Very High Extra High
Required software reliability 0.75 0.88 1.00 1.15 1.40
Database size 0.94 1.00 1.08 1.16
Product complexity 0.70 0.85 1.00 1.15 1.30 1.65
Execution time constraint 1.00 1.11 1.30 1.66
Main storage constraint 1.00 1.06 1.21 1.56
Virtual machine volatility 0.87 1.00 1.15 1.30
Computer turnaround time 0.87 1.00 1.07 1.15
Analyst capabilities 1.46 1.19 1.00 0.86 0.71
Applications experience 1.29 1.13 1.00 0.91 0.82
Programmer capability 1.42 1.17 1.00 0.86 0.70
Virtual machine experience 1.21 1.10 1.00 0.90
Programming language experience 1.14 1.07 1.00 0.95
Use of modern programming practices 1.24 1.10 1.00 0.91 0.82
Use of software tools 1.24 1.10 1.00 0.91 0.83
Required development schedule 1.23 1.08 1.00 1.04 1.10